Mater Dei Hospital

BURNS DRIVE
MALINDELA
BULAWAYO
ZIMBABWE                          

P O BOX 2133
BULAWAYO
TEL (263-9)  240 000 / 5
FAX (263-9) 242 106
E-mail magskriel@mac.com

RECONSTRUCTION


Date: 23 Sept 2007
Photo's & recordings of the 5th Floor opening ceremony

Click on photo to enlarge:-

Opening Fifth Floor Mater Dei Hospital - June 2007 Mater Dei Hospital - June 07
   
Bulawayo Mater Dei Hospital Opening ceremony - June 07
   
Opening ceremony - June 07 Opening Mater Dei 5th floor
   

Date: 19 Oct 2006
Reconstruction continues, with donations from wonderful kind benefactors - both local and from around the world!


Ceiling work Oct 2006 The Building Team
   
Tileing Aug 2006 Sophisticated bedhead trunking
   
Smoke-detectors Almost complete wards
   
 
Plastering/tiling  
   
Baths & basins July 2006 Benefactor has Donated
   
Containers Full of New Equipment Donations from all over the world
   
Fire Sprinklers Hospital Furniture by Alpha Steel
   
New Cupboard Window & Door Frames New Electrical Conduits
   
 
New Porcelain Sanitary ware  
   
Finished Roof 1 Dec 05 Roof Team 1 Dec 05
   
Roof Team - 1 Dec 05 Team Thanks - 1 Dec 05
   

Date: 02 December 2005
The Roof at Mater Dei has been completed and a small ceremony was held, where Sr Maureen Jamieson and Sr Isabel Courtney presented Certificates of Appreciation to most of the work team who had rebuilt the roof.
Eng Peter Edmeades and Trevor Heath were commended for the simplified and improved roof design that will result in greater fire protection and improved maintenance access.
Peter Goosen was one of the first people at the scene of the fire and did not leave the site until the fire and it safety problems were fully settled in the early hours of Saturday morning. He was there offering his support at the initiating meeting of the rebuild committee at 7.30am on Saturday morning. He and his church team commenced work straight after the fire, and continued in support of a team assigned by Sullivans Engineering. Peter helped keep up a very high standard of accuracy and safety and continued to assist and direct much of the operations.
The workforce was soon joined by an experienced construction foreman, Joseph Dube, who had supervised several projects, like bridges, factories, an elevated water tower and plenty of structural steel and roofing. On the day that Peter Edmeades and John Sullivan were discussing the need for full-time supervision, John Sullivan was suddenly hooted at by his ex-foreman in his pickup truck at a traffic light. He had not seen him for as much as 2 years and there he was out of the blue! He was invited to take on this important task and accepted without hesitation.
N Stipinovich helped by making the trusses and their labour co-operative, Nansi-Sipho, provided hoisting plus bricklayers and plasterers.
The work was completed accident-free and in a very satisfactory time. As the last certificates were being given the brooding clouds began to rain and steady rain was still falling on Friday morning.

Roofing / Clouds Sat 12 Nov Inner walls 19 Nov 05
   
Joseph South Roof South Fascias - Our prayers are with the
men who are re building our Hospital
   
Pearson pantiling 15-Oct-05 - Close up of roof tilers Half the New Roof is complete 2-Nov-05
   

New bolted Trusses awaiting errection

Pan Tile Roofing

Trusses Ready for Lifting to the Roof

Pan-Tile Roofing On Site

First Trusses on West end

Truss spanning onto Steel girder

First Trusses Erected

Steel Beams to sections of outer walls

Alignment on First trusses

Looking West to first trusses on West end

First Trusses go in place

A view looking West

 As Construction Continues

View of Hoist to South West of 5th Floor
View from North Balcony into a Ward

Progress as 15 October 2005

View looking West along 5th Floor Corridor